EXECUTION OF START-AND-ADJUSTMENT WORKS FOR UNITS OF ROMELT PLANT, REPUBLIC OF THE UNION OF MYANMAR

07.12.2016
EXECUTION OF START-AND-ADJUSTMENT WORKS  FOR UNITS OF ROMELT PLANT,  REPUBLIC OF THE UNION OF MYANMAR

August-November, 2016, SE «UkrRTC «Energostal» with its strategic partner LLC «ETC «Rosenergostal» executed successfully individual and complex testing of equipment of energy units of Romelt plant in Pang Pet city, Republic of the Union of Myanmar.

       Cold starting of energy units was executed 27 October 2016 including main and auxiliary process equipment of plant: recycling water supply system, furnace cooling system, chemical water deionization installation, ore-preparation and coal-preparation equipment, automatic fire-fighting system, large mechanical equipment of wet material supply bunkers, cooling towers and pump stations, gas cleaning systems (with starting of two smoke exhausts DN-26х2) and other units. Adjustment and mounting works for electric equipment, automatic process control system equipment and instrumentation and automation equipment were made.

        In future SE «UkrRTC «Energostal» will plan finishing start-and-adjustment works for Romelt plant and realize hot starting with setting equipment for designed parameters.